At a glance
Microcement has no tile grout lines, but manufacturers require substrate movement joints to be kept.
Over old tiles, the joints must be filled and levelled first.
Before a quote, show movement joints, cracks and junctions between materials in photos.
Where the seamless look comes from
Tiles are laid as separate pieces with a joint between them. Microcement is applied in layers over the whole surface, so there is no grid of joints. Manufacturers describe it as a continuous or seamless coating — Topciment and Festfloor, for example, describe their systems that way.
It is a thin layer. In technical data sheets the total system thickness is usually around 1 to 3 mm: Topciment recommends 1–3 mm, and Festfloor gives about 1.5–2 mm for FESTWALL Life. The thickness depends on the product, so ask which layers the proposed system consists of.
Fewer joints means fewer places to clean. Manufacturers say in their marketing that the absence of grout makes cleaning easier, but no technical data sheet contains a test that measures it.
Substrate movement joints stay
Movement joints let the substrate and the building structure move. Microcement does not remove them. Topciment’s system description says expansion joints must always be respected, and Ideal Work says the control joints of the substrate must be kept. Holcim’s screed guide notes that the structural movement joints of the building should be reflected in the screed.
If a joint keeps moving, its line may show on the finished surface as well. Kerakoll explains that closed joints and cracks that keep working can be seen against the light as slight ridges or hollows. That is why what to do with a joint is decided before the work, not afterwards.
Joints in old tiles
When microcement goes over existing tiles, the joints must be filled first. The FESTWALL Life data sheet says so directly: gaps and joints must be filled. Topciment sells a separate product for filling tile joints.
Filling the joints does not replace an assessment of the tiles themselves. Loose, cracked or damp tiles need a separate decision — our guide to microcement over old tiles explains it.
Where lines can remain on the finished surface
Mark these places on a plan or in photos and discuss them before the quote, together with how each will be finished:
- substrate and structural movement joints that must be kept;
- the border between areas applied separately, for example between rooms or at a threshold;
- junctions with another material: timber, tiles, a skirting, joinery;
- places where the substrate has cracked — substrate cracks can transfer to the thin finishing layer.
What to prepare before talking to a contractor
Photograph the whole surface and take close-ups of movement joints, cracks, thresholds and junctions. Say whether there are tiles, screed or another substrate underneath, and whether there is underfloor heating. This shows where the surface can be continuous and where a joint needs a solution.
What drives the price per square metre is explained on our microcement cost page.
What this guide is based on
We use technical data sheets and instructions from Topciment, Festfloor, Ideal Work and Kerakoll, and Holcim’s screed guide. They are examples of what manufacturers state. This does not mean VPD Design installs each of these systems — the specific solution is decided after assessing the site.
VPD Design
Want a floor without grout lines?
Send photos of the whole surface and of any joints and cracks. We will tell you what needs checking before the scope is agreed.
Send floor photos